Go directly to the text content

Ventilation of Electric Mines (VEM)

Important results from the project

We managed to do a preliminary quantification on how much changes on an underground mine ventilation can be made when BEVs are the main production machines. However, as described in the attached public final report, this quantification is only for one production area so it is still too early to conclude that this quantification is valid for the whole mine.

Expected long term effects

This project is expected to change how underground mine ventilation is designed when BEVs are used as the main production machines. This may include reducing the size of ventilation fans and developing new ventilation system to ventilate battery charging bays.

Approach and implementation

The project was carried out in 4 work packages: 1. Literature review and field-testing preparation 2. Field testing of reducing airflow in the BEV trial area 3. Simulating ventilation of the BEV trial area 4. Identifying key challenges and writing project report These were found to be the right activities. Everything went according to the plan and timeline albeit with a slight change in how the airflow was varied as reported in the situation report. No external factors influencing the project.

The text has been written by the project team. The content is copied from the funding agency’s website and has not been reviewed by the Program Office.

Project title
Ventilation of Electric Mines (VEM)
Registration number
2024-02665
Coordinator
Luleå University of Technology - Inst för samhällsbygg & naturresurser
Call
2024-01480 Impact Innovation: Feasibility studies within Technological Action Areas in the program Metals & Minerals
Project duration
November 2024 - June 2025
Project type
Feasibility study
Responsible funding agency
Vinnova

For further information about the project, please visit Vinnova